Total Project Cost versus time curve is:
कुल परियोजना लागत बनाम समय वक्र है:
A.
Parabolic curve
B.
U – shaped curve
C.
Linear
D.
Log curve
Answer ( Option B)

U – shaped curve

Solution

  • Total Project Cost and Optimum Duration: The total project cost is the sum of the direct cost and indirect costs. It is U-shaped curve.
  • We find that the minimum total cost is obtained at some duration known as the optimum duration to , the corresponding cost is known as the minimum cost.
  • If the project duration is increased, total cost will increase, while if project duration is decreased to the crash value project cost will be the highest.