Question
Among the following, the correct sequence of WBM construction will be:
i. Preparation of subgrade
ii. Spreading of coarse aggregates 
iii. Application of binding material 
iv. Application of screenings
v. Provision of lateral confinement
A.
i, ii, iv, iii, v
B.
i, iv, ii, iii, v
C.
i, v, ii, iv, iii
D.
ii, i, iv, v, iii
Answer ( Option C)

i, v, ii, iv, iii

Solution

Water Bound Macadam Roads: 
• In this method, the broken stones of the base course and surface course, if any, are bound by the stone dust in presence of moisture. 
• The roads whose wearing course consist of clean crushed aggregates, mechanically interlocked by rolling and bound together with filler material and water and laid on a well compacted base course, is called water bound macadam road. 
• The correct sequence of WBM preparation is: 
   1. Preparation of subgrade
   2. Provision of lateral confinement 
   3. Spreading of coarse aggregates 
   4. Application of screenings 
   5. Application of binding material

Online Classes

We care about our students



Online Classes
Register Now
Test Series
Register Now
Job Notification
Job Notification

Daily Quiz

RPSC-AE, RSMSSB-JE, SSC-JE, RRB-JE, PSU's