Question
Calculate the expected time for the given activity, where t0 = 22 days, t1 = 30 days, tp = 50 days.
fdlh nh xbZ xfrfof/k ds fy, lEHkkfor le; dh x.kuk djsa] tgk¡ t0 = 22 fnu, t1 = 30 fnu, tp = 50 fnu gSA
A.
12 days
B.
32 days
C.
34 days
D.
36 days
Answer ( Option B)

32 days

Solution