Size of brick = 190 x 90 x 90 mm3
Let mortar thickness = 10 mm
Size of brick with mortar = 0.19 + 0.01 = 0.20 m, 0.09 + 0.01 =
0.1 m, 0.09 + 0.01 = 0.1 m
Volume of brick with mortar = 0.2 x 0.1 x 0.1 = 0.002 m3
No. of bricks in 1 m3 = 1/0.002 = 500 Nos.
Volume of 500 bricks without mortar = 500 x 0.19 x 0.09 x 0.09 =
0.7695 m3
Volume of mortar = 1 – 0.7695 = 0.2305 m3
18% extra mortar for frog filling and wastage is considered.
So volume of mortar = 1.18 x 0.2305 = 0.27199 m3
Volume of dry mortar = 1.3 x 0.27199 = 0.353 m3
Percentage of dry mortar = (0.353/1) x 100 = 35.3%