Duration along the critical path defines which of the following?

A. Shortest duration needed

B. Shortest duration permissible

C. Longest duration needed

D. Longest duration permissible 

Select the code for the correct answer from the options given below :
A.
A and B only
B.
A and D only
C.
B and C only
D.
C and D only
Answer ( Option B)

A and D only

Solution

Critical path is shortest duration needed and longest duration permissible. Critical path method does not take resources limitations into account.