Question
How much time duration is required for dummy activity?
vkHkklh ⟨Meh⟩ गतिविधि ds fy, fdrus le; dh vofèk vko';drk gksrh gS\
A.
Ideal duration
B.
No duration
C.
Continuous duration
D.
Constant duration
Answer ( Option B)

No duration

Solution

Dummy activity:
It is a type of activity in the network which neither consumes any time nor resource.
It is an artificial activity.
It is represented by a dashed arrow and identified by the terminal node or event to which it connects.
It maintains the uniqueness of the activity 
It acts as a connecting link for control purposes.