In load flow study, a PV bus is treated as a PQ bus when
Voltage
limit is violated
Active
power limit is violated
Phase angle is high
Reactive power limit is violated
Reactive power limit is violated
In
load flow study, a PV bus is treated as a PQ bus when reactive power limit is
violated.
Hence,
the correct option is (D).