LOADING
Question
In resource levelling:
A.
total duration of project in reduced
B.
total duration of project is increased
C.
uniform demand of resources is achieved
D.
cost of project is controlled
Answer ( Option B)

total duration of project is increased

Solution

• In the resource levelling process activities are rescheduled such that maximum demand of resources

  requirement does not exceed the limit of availability of resources. 

• During this process at first re-arrangement of activities having floats is done. Even if by doing so, resource

  requirement is more than availability of resources, then duration of some activities is increased such that

  resource requirement of these activities is reduced. Hence project duration might get increased during the

  process of resource levelling.

Online Classes

We care about our students



Online Classes
Register Now
Test Series
Register Now
Job Notification
Job Notification

Daily Quiz

RPSC-AE, RSMSSB-JE, SSC-JE, RRB-JE, PSU's