In substations, the breaker maintenance is
provided in the
double busbar scheme
single busbar scheme
main and transfer bus scheme
all of these
main and transfer bus scheme
Main bus and transfer bus- In
this arrangement one or more busses is added to the single bus substation
scheme. One or more circuit breakers may be used in this arrangement to make connection
between the main and transfer bus in the main and transfer bus configuration,
the protective relay scheme is quite
complex due to the requirement of the tie breaker to handle each situation for
maintenance of any other circuit breaker. This bus scheme is more costly than
the single bus configuration but is more reliable and can be easily expanded.
Hence, the correct option is (C).