Question

Match List I (Inputs into Networks) with List II (Basis) and select the correct answer :        

List-I

List- II

A.

Activity Time

1

Availability of resources is not discussed

B.

PERT durations

2

Senior managements involvement is assumed

C.

WBS

3

Total cost of each activity is considered

D.

Interfaces

4

Needed supervisory inputs are considered

Code:   

        A          B          C          D

A.
3          1          4          2
B.
3          1          2          4
C.
4          2          1          3
D.
4          2          3          1
Answer ( Option A)

3          1          4          2

Solution

 PERT do not consider resource availability.

 In CPM, to calculate activity time, total cost of each activity is considered

 WBS is a deliverable oriented grouping of project elements that organizes and defines the total scope of the project. 

 For interfaces, the senior managements involvement is considered to decide the target dates.

Online Classes

We care about our students



Online Classes
Register Now
Test Series
Register Now
Job Notification
Job Notification

Daily Quiz

RPSC-AE, RSMSSB-JE, SSC-JE, RRB-JE, PSU's