LOADING
Question
Pick up the incorrect statement from the following.
fuEufyf[kr esa ls xyr dFku dk pquko dhft,A
A.
Lead is the average horizontal straight distance between the borrow pit and the place of spreading soil
B.
The lead is calculated for each block of the excavated area
C.
The unit of lead is 50 m for a distance upto 500 m
D.
The unit of lead is 1 km where the lead exceeds 2 km
Answer ( Option D)

The unit of lead is 1 km where the lead exceeds 2 km

Solution

Earth work may be either earth excavation or earth filling or Sometimes both.
Basically the volume of earthwork is computed from length, breadth, and depth of excavation or filling.
However the payment for the earthwork is made according to this volume as well as the lead and lift with regard to area of disposal.
Lead is the average horizontal distance b/w site of earthwork and the area of disposal.
Lift is the average vertical distance b/w level of excavation and to the place of spreading or heaping.

Online Classes

We care about our students



Online Classes
Register Now
Test Series
Register Now
Job Notification
Job Notification

Daily Quiz

RPSC-AE, RSMSSB-JE, SSC-JE, RRB-JE, PSU's