Question

Portion of the installed reserve kept in operable condition but not placed in service to supply the peak load is known as ________. 

A.

operating reserve     

B.

spinning reserve 

C.

cold reserve 

D.

cold reserve 

Answer ( Option C)

cold reserve 

Solution

●The generating capacity available to the system within short duration of time to meet the demand when a generator goes down is known as operating reserve.

●The generation capacity that is on line but overloaded and that can respond within minutes to compensate for generation is known as spinning reserve.

●Portion of the installed reserve kept in operable condition but not placed in service to supply the load is known as cold reserve.

●The reserved capacity which can be made available quickly is known as hot reserve.

Hence, the correct option is (C).

Online Classes

We care about our students



Online Classes
Register Now
Test Series
Register Now
Job Notification
Job Notification

Daily Quiz

RPSC-AE, RSMSSB-JE, SSC-JE, RRB-JE, PSU's