The earliest date and the latest date of events 3 and 10 are given in the figure below. Activity E is

connecting both the events and its duration is 10 weeks. The independent float of the activity is 

         

 

A.
5 weeks
B.
10 weeks
C.
15 weeks
D.
20 weeks
Answer ( Option A)

5 weeks

Solution

FID = (EST)10 — (LFT)3 — tij= 40 – 25 – 10 = 5