The expected time (te) of a PERT activity in terms  of optimistic times (to), pessimistic time (tp) and most likely time (tm) is given by
A.
B.
C.
D.
Answer ( Option A)

Solution

The expected time (te) of PERT activity in terms of optimistic time (t0), pessimistic time (tp) and most likely time (tm) is given by, 