The minimum period before stricking the props to a beam spanning 7.5 m is 
A.
3 days
B.
16-24 h
C.
7 days
D.
21 days
Answer ( Option D)

21 days

Solution

Type of formwork Minimum period before removal Placing condition Minimum grade of concrete
Vertical formwork to columns, walls, beam 16-24 h 25 - 75 M20
Soffit formwork to slabs 3 days 50 - 100 M25
Soffit formwork to beams 7 days 75 - 100 M30
Props to slabs : (i) Spanning up to 4.5 m (ii) spanning over 4.5m 7 days & 14 days 100 - 150 M35
Props to beams and arches (i) Spanning up to 6m (ii) spanning over 6m 14 days & 21 days 150 - 200 M40