The project activities are given in the following table along with the duration and dependency.
Activities                   Duration (days)            Depends on
P                                   10                                   -
Q                                   12                                  -
R                                    5                                   P
S                                    10                                 Q
T                                    10                                 P, Q
Which one of the following combinations is correct?
A.
Total duration of the project = 22 days & Critical path is Q  S
B.
Total duration of the project  = 20 days & Critical path is Q  T
C.
Total duration of the project = 22 days & Critical path is P T
D.
Total duration of the project = 20 days & Critical path is P R
Answer ( Option A)

Total duration of the project = 22 days & Critical path is Q  S

Solution

Online Classes

We care about our students



Online Classes
Register Now
Test Series
Register Now
Job Notification
Job Notification

Daily Quiz

RPSC-AE, RSMSSB-JE, SSC-JE, RRB-JE, PSU's