Total float can be expressed as-
1. Latest start time - earliest start time
Total float :
• Float is difference between maximum time available and actual time required for the completion of the
activity.
• FT = (Maximum available time) – (Actual time required)
• Maximum available time we can get when activity starts at earliest start time and finish by latest finish
time i.e.,
• Maximum available time = LFT - EST
• Actual time required for performing an activity is the estimated activity time tij
FT = LFT - EST – Tij
FT=LST- EST
Or
FT=LFT - EFT