Which of the following estimate is carried out if the sanctioned estimate exceeds 5% due to change in the price?
;fn ewY; esa ifjorZu ds dkj.k LohÑr vuqeku 5% ls vf/kd gks tkrk gS] rks fuEufyf[kr esa ls dkSu lk vuqeku yxk;k tkrk gS
A.
Detailed estimate

विस्तृत अनुमान

B.
Plinth area estimate

प्लिंथ क्षेत्र का अनुमान

C.
Preliminary estimate

प्रारंभिक अनुमान

D.
Revised estimate

संशोधित अनुमान

Answer ( Option D)

Revised estimate

संशोधित अनुमान

Solution

Detailed Estimate :
• It is the accurate estimate prepared by work.
• It consists of reports, general specifications, drawing and analysis of rates.
• It is prepared for technical sanction, for arranging contract and for execution of project.
Plinth area estimate :
• It is an approximate estimate calculated for covered area by taking external dimension of the building at the floor level.
Preliminary Estimate
• It is an approximate estimate to find out an approximate cost in a short time.
• It enables the authority concerned to consider the financial aspect of scheme, for according sanction to the same.
Revised Estimate
It is prepared when original sanctioned estimate is likely to exceed by more then 5%.
• It is also prepared when there are material deviation from original proposal even through cost may be met from sanctioned cost.

Online Classes

We care about our students



Online Classes
Register Now
Test Series
Register Now
Job Notification
Job Notification

Daily Quiz

RPSC-AE, RSMSSB-JE, SSC-JE, RRB-JE, PSU's